Deployment of carbon management and CO2 capture and utilization technologies

First written in FY2018. 11 of 13 entries say "Advanced", first in FY2020. Latest entry: FY2026.

13entries
9years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2018AdvancedFY2020 – FY2023-Q3AdvancedFY2024-Q1 – FY20262018: 120182019: 020192020: 220202021: 020212022: 220222023: 320232024: 320242025: 120252026: 12026
Same theme, other companies
Promoting carbon neutrality through renewable energy and decarbonization technology developmentA theme 26 companies write about · 0 as a headwind · 28 as a tailwind

13 other companies' latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 26 companies compared. The sentences above are computed from all 26.
Full recordFilings, disclosures and news, newest first
  1. FY2026AdvancedAnnual report

    「We have begun strategic collaboration with SLB Capturi and its parent company, SLB, concerning CO2 separation and capture technology, with the aim of implementing it in the Asia-Pacific region, including Japan, and the Middle East.」

    The CO2 capture initiative has progressed from the study phase to the launch of strategic collaboration and the implementation phase in the Asia-Pacific and Middle East regions.
  2. FY2026-H1AdvancedAnnual report

    「The Company entered into a memorandum of understanding with SLB Capturi, a leading provider of industrial CO2 capture technology, and its parent company SLB, concerning the capture of CO2 in post-combustion flue gas, and began discussions on potential strategic collaboration with the SLB Group. In addition to winning EPC projects for CO2 capture facilities through collaboration with the SLB Group, the JGC Group plans to consider providing technical consulting that combines various approaches, including research, analysis and evaluation, and simulation-based risk assessment focused on energy and the environment.」

    The CO2 capture initiative has progressed to the signing of a memorandum of understanding with SLB Capturi and SLB and the launch of discussions on strategic collaboration, with the potential provision of technical consulting services added to the scope alongside EPC.
  3. FY2025-H1AdvancedAnnual report

    「In a public call for proposals by the Japan Organization for Metals and Energy Security for “design work and other services related to advanced CCS projects” for fiscal 2024, the Company, together with partner companies including Japan Petroleum Exploration Co.,Ltd., was awarded design work and other services for a CCS project to inject and store CO2 emitted by multiple industries, including in the Setouchi area, offshore Sarawak, Malaysia.」

    For the CCS business, we were commissioned to carry out design work and related activities for an advanced CCS project that would collect CO2 from multiple industries in the Setouchi area and inject and store it offshore Malaysia.
  4. FY2024AdvancedAnnual report

    「In addition to JFE Steel Corporation, The Chugoku Electric Power Company,Incorporated and Japan Gas Line Co., Ltd. have joined the joint study being conducted by us, Japan Petroleum Exploration Co.,Ltd. and others to develop a CCS value chain originating in Japan. We have begun examining the development of a CCS value chain, including the facilities and costs required to separate and capture CO2 emitted at steelworks and power plants in Japan owned by JFE Steel Corporation and the Chugoku Electric Power Group, transport liquefied CO2 by sea to Malaysia, including domestic coastal transport in the Setouchi area, and receive and store it.」

    The Chugoku Electric Power Company and Japan Gas Line have joined the CCS joint study, expanding its scope to cover capture from steelworks and power plants, domestic transport, marine transport to Malaysia, and receiving and storage.
  5. FY2024-Q3AdvancedAnnual report

    「In addition, the Company entered into a basic agreement with PETRONAS CCS Ventures SDN BHD, a subsidiary of Malaysia's national energy company, together with Japan Petroleum Exploration Co.,Ltd. and Kawasaki Kisen Kaisha,Ltd., concerning a study of the commercialization of a CCS business in Malaysia, and coordinated it with the aforementioned study on establishing a CCS value chain. In Indonesia, the Company began a joint study with JERA Co., Inc. and Indonesia's state-owned power company on introducing and commercializing CCS for thermal power plants in the country.」

    The CCS initiative has progressed to the signing of a basic agreement with a PETRONAS subsidiary to study commercialization and the launch of a joint study targeting a thermal power plant in Indonesia.
  6. FY2024-Q1AdvancedAnnual report

    「JFE Steel Corporation has newly joined the joint study being conducted by us, Japan Petroleum Exploration Co.,Ltd. and Kawasaki Kisen Kaisha,Ltd. to develop a CCS value chain originating in Japan. We have begun examining the development of a CCS value chain, including the facilities and costs required to separate and capture CO2 emitted at JFE Steel Corporation's steelworks in Japan, transport liquefied CO2 by sea to Malaysia and receive it there.」

    JFE Steel has joined the study of a CCS value chain from Japan to Malaysia, and concrete studies have begun covering the separation and capture of CO2 at steelworks, liquefaction, marine transport and receiving facilities.
  7. FY2023SoftenedAnnual report

    「Following basic engineering and construction of the demonstration facilities, we expect to begin CO2 injection and monitoring around the latter half of the 2020s.」

    For CCS at the Gundih gas field, the timeline changed from the previous assumption of around 2025 to the latter half of the 2020s.
  8. FY2023-Q3AdvancedAnnual report

    「In addition, JGC Global Corporation participated in a joint study on carbon capture and storage (CCS) in Malaysia promoted by Petronas and Japan Petroleum Exploration Co.,Ltd. It also participated in a joint study with Petronas and JX Nippon Oil & Gas Exploration Corporation on building a specific CCS supply chain comprising the separation, capture, transportation, injection and storage of CO2 emitted from industrial facilities in Malaysia, as well as CO2 from outside Malaysia, including Japan. In addition, it signed a memorandum of understanding on GHG measurement at an ammonia production site in Indonesia, and actively pursued the decarbonization and lower-carbon use of fossil energy.」

    Regarding CCS, the joint study in Malaysia expanded to consideration of a specific supply chain for separation, capture, transportation, injection and storage, while in Indonesia a memorandum of understanding on GHG measurement was also signed.
  9. FY2023-Q2AdvancedAnnual report

    「In addition to participating in a joint study on carbon capture and storage (CCS) in Malaysia promoted by a Malaysian state-owned energy company and Japan Petroleum Exploration Co.,Ltd., we actively pursued the decarbonization and lower-carbon use of fossil energy, including by signing a memorandum of understanding on greenhouse gas (GHG) measurement at an ammonia production site in Indonesia.」

    Regarding carbon management, efforts progressed through participation in a joint CCS study in Malaysia and the signing of a memorandum of understanding on GHG measurement at an ammonia production site in Indonesia.
  10. FY2022AdvancedAnnual report

    「Going forward, following the basic design and construction of the demonstration facility, we plan to begin CO2 injection and monitoring around 2025.」

    For carbon management, the initiative progressed from a feasibility study for the commercialization of CCS at Indonesia's Gundih gas field to plans to begin CO2 injection and monitoring in 2025 following basic design and construction.
  11. FY2021-Q2AdvancedAnnual report

    「In July of this year, the development of technology to permanently fix CO2 using calcium contained in construction waste and magnesium contained in seawater and waste brine, promoted jointly with universities and other companies, was selected for NEDO's commissioned research and development project.」

    The development of CO2 fixation technology was selected for NEDO's commissioned research and development project as joint research with universities and other companies.
  12. FY2020AdvancedAnnual report

    「For CO2-EOR, we developed technology using a specialized ceramic membrane to efficiently separate and capture CO2 produced together with crude oil, and began a demonstration test in Texas, United States.」

    Regarding carbon management technology, the development of ceramic membrane technology for CO2-EOR and the start of a demonstration test in Texas, United States, were described.
  13. FY2018First statedAnnual report

    「We continue to build up technologies and expertise in each element of the carbon management cycle: controlling CO2 emissions, separation and capture, effective utilization and storage, and resource regeneration.」

    We are building expertise across a series of technology areas covering CO2 emissions control, separation and capture, effective utilization and storage, and resource regeneration, and deploying solutions for CCS and CO2-EOR.
Moved together

"Broad-based domestic and international EPC order-taking activities and award of a Philippine thermal power plant project" moved the same way as this thread, in the same document, in 9 of its 13 moves.

977766★123456
  1. ★This thread
  2. 1Broad-based domestic and international EPC order-taking activities and award of a Philippine thermal power plant project9×
  3. 2Outlook for rising global energy demand7×
  4. 3Building environmental businesses through the establishment of the Sustainability Co-Creation Department7×
  5. 4Demonstration and development of a commercial-scale supply chain for SAF made from used cooking oil7×
  6. 5Operating loss in the comprehensive engineering business6×
  7. 6Expectations for progress on capital investment plans for large-scale oil and gas projects and other projects6×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Jgc Holdings's next results are scheduled for 2026-11-11. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.