Modular construction methods for large-scale LNG projects
First written in FY2017-Q2. 6 of 13 entries say "Restated". Latest entry: 2026-08-07.
No other company in this theme has enough history to compare yet.
- FY2023AdvancedAnnual report
「The company has implemented AWP in the construction work of multiple ongoing projects and is expanding its use of AWP management to design and procurement operations to extend its benefits across those functions.」
Large-scale modular construction and AWP progressed to the implementation stage in the construction work of multiple ongoing projects, with expansion into design and procurement operations also under way. - FY2022AdvancedAnnual report
「The company is implementing large-scale modular construction and construction management using AWP to improve project execution efficiency, while expanding the scope of technology applications to robotics, automation, 3D printing, small-scale modular construction and remote operations,」
In addition to large-scale modular construction and AWP implementation, the company expanded the scope of technology applications to robotics, automation, 3D printing, small-scale modules and remote operations. - FY2022-Q3RestatedAnnual report
「As part of its efforts toward the full-scale introduction of 3D printers in construction work and, ultimately, the digital transformation of plant construction, the Group began demonstrating the effectiveness of construction 3D printers at a domestic plant construction site.」
The initiative to demonstrate the effectiveness of construction 3D printers has been reaffirmed. - FY2022-Q1AdvancedAnnual report
「As part of its efforts to fully introduce 3D printers into construction work, the company began demonstrating the effectiveness of construction 3D printers at a domestic plant construction site.」
As part of the advancement of project execution technology, including large-scale modular construction, the company began demonstrating the effectiveness of construction 3D printers at a domestic plant construction site. - FY2020AdvancedAnnual report
「The group is implementing large-scale modular construction methods and construction management using AWP (Advanced Work Packaging) to improve project execution efficiency. It is also taking on the implementation of further new construction methods, including robotics, automation, 3D printing and small-scale modular construction, the introduction of enabling technologies such as new materials and AI in design, and the broader adoption of AWP across the EPC value chain,」
In addition to adopting modular construction methods, the company is implementing AWP and expanding its scope to include new construction methods and enabling technologies such as robotics, 3D printing, small-scale modules and AI-assisted design. - FY2019-Q3RestatedAnnual report
「To further strengthen its ability to win and execute projects, in April of the same year the company agreed to collaborate with China Offshore Engineering Co., Ltd. (COOEC), which has strong module fabrication capabilities, on modular construction methods effective for LNG and other projects where construction is difficult at the plant site,」
The agreement to collaborate with COOEC on modular construction methods was reiterated and continues to be positioned as a measure to strengthen execution capabilities for LNG projects. - FY2019-Q2RestatedAnnual report
「To further strengthen its ability to win and execute projects, in April of the same year the company agreed to collaborate with China Offshore Oil Engineering Co., Ltd. (COOEC), which has strong module fabrication capabilities, on modular construction methods effective for LNG and other projects where construction is difficult at the plant site,」
The agreement to collaborate with COOEC on modular construction methods was reiterated and positioned as a means of strengthening project execution capabilities. - FY2019-Q1AdvancedAnnual report
「To further strengthen its ability to win and execute projects, in April of the same year the company agreed to collaborate with China Offshore Oil Engineering Co., Ltd. (COOEC), which has strong module fabrication capabilities, on modular construction methods effective for LNG and other projects where construction is difficult at the plant site. In May of the same year, it agreed to collaborate with U.S. construction company S&B Engineers and Constructors, Ltd. (S&B), which has extensive experience in the Gulf Coast region, to jointly win and execute projects in the U.S. market, where numerous projects are planned.」
The agreement to collaborate with COOEC, which has module fabrication capabilities, gave concrete form to the project execution framework for modular construction on large-scale LNG projects. - FY2018RestatedAnnual report
「The Group will work to strengthen its order-taking competitiveness by further enhancing its technical capabilities in the LNG field, pursuing more advanced project execution technologies such as modular construction, promoting the use of IoT to enhance the business value of plants, and improving technical capabilities in the pharmaceutical field to address advanced medical care.」
The company has reaffirmed its policy of using advances in project execution technology, including modular construction, to strengthen its competitiveness in winning orders. - FY2017-Q2First statedAnnual report
「Construction using a new method, known as modular construction, is reaching its peak. Under this method, plants are built in functional units at sites across Asia, transported by large vessels to the final construction site, and assembled into a single plant.」
Modular construction, in which functional plant units are built in Asia and assembled after transport, is described as a specific construction method.