Completion Delays and Liquidated Damages on Solar Power Plant Construction Projects
First written in FY2021-Q2. 3 of 5 entries say "Restated". Latest entry: FY2024.
5entries
5years
0from disclosures
How it moved
Same theme, other companies
Recognition of Contract-Breach LossesA theme 12 companies write about · 13 as a headwind · 0 as a tailwind
2 other companies' latest entry also says "Restated".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2024RestatedAnnual report
「太陽光発電所建設工事において予定された発電量が実現できないことから、契約に基づく、逸失利益相当分を損害賠償金の発生見込額として計上しております。」
太陽光発電所建設工事について予定発電量未達と逸失利益相当の損害賠償金発生見込額の計上が通期でも確認されている。 - FY2023MaterialisedAnnual report
「太陽光発電所建設工事において予定された発電量が実現できないことから、契約に基づく、逸失利益相当分を損害賠償金の発生見込額として計上しております。」
太陽光発電所建設工事について、予定発電量未達が実際に発生し、逸失利益相当分として工事損失引当金繰入額99百万円が計上された。 - FY2022-Q2RestatedAnnual report
「太陽光発電所建設工事において工事完成が遅延することから、契約に基づく遅延違約金の発生見込額を計上しております。」
太陽光発電所建設工事の完成遅延と、それに伴う契約上の遅延違約金の発生見込額の計上が、前四半期に続き注記されている。 - FY2021-Q3RestatedAnnual report
「太陽光発電所建設工事において工事完成が遅延することから、契約に基づく遅延違約金の発生見込額を計上しております。」
太陽光発電所建設工事の完成遅延と、それに伴う契約上の遅延違約金の発生見込額の計上が、同じ内容で再確認されている。 - FY2021-Q2MaterialisedAnnual report
「太陽光発電所建設工事において工事完成が遅延することから、契約に基づく遅延違約金の発生見込額を計上しております。」
太陽光発電所建設工事の完成遅延により、契約に基づく遅延違約金の発生見込額として工事損失引当金繰入額3億10百万円を計上している。