Tokyo Energy & Systems (1945) · InitiativeDecline in cogeneration equipment construction

Initiatives in Cogeneration-Related Construction

First written in FY2018-Q2. 5 of 11 entries say "Restated". Latest entry: FY2022-Q1.

11entries
5years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2018-Q2 – FY2019AdvancedFY2020-Q1OtherFY2021-Q1 – FY2022-Q12017: 12018: 320182019: 320192020: 220202021: 22021
Same theme, other companies
Cogeneration-Related Construction and Declining OrdersA theme 1 companies write about · 1 as a headwind · 0 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2022-Q1Decline in cogeneration equipment constructionAnnual report

    「Revenue amounted to ¥10.804 billion, compared with ¥12.622 billion in the same period of the previous year, as construction work for thermal power generation facilities increased, but cogeneration facility construction and scheduled inspection work on thermal power generation facilities decreased year on year.」

    Construction work for cogeneration facilities declined from the same period of the previous year and was cited as a factor behind the decline in sales.
  2. FY2021-Q3Increase in sales from construction work for cogeneration facilitiesAnnual report

    「Meanwhile, sales were ¥39,657 million, down 11.6% year on year, as construction work for nuclear power generation facilities' safety measures and cogeneration facilities increased, but construction work for thermal power generation facilities and solar power generation facilities declined, while construction plans were postponed or cancelled due to the spread of COVID-19.」

    Construction work for cogeneration facilities was cited as a factor behind the increase in sales, while total sales declined.
  3. FY2021-Q2Decline in cogeneration equipment constructionAnnual report

    「Orders received in the six-month period ended 30 September amounted to ¥26.871 billion, up 0.2% year on year, as the increase in scheduled inspection work on thermal power generation facilities and safety-related work at nuclear power plants outweighed decreases in cogeneration facility construction, thermal power generation facility construction and solar power generation facility construction.」

    Construction work for cogeneration facilities was cited, together with construction work for thermal power generation facilities and solar power generation facilities, as a factor behind the decline in orders.
  4. FY2021-Q1Decline in cogeneration equipment constructionAnnual report

    「Order intake for the cumulative first quarter of the consolidated fiscal period was ¥9,701 million, down 27.3% year on year, due to decreases in construction work for cogeneration facilities and construction work for thermal power generation facilities, among others.」

    Construction work for cogeneration facilities was cited as a factor behind the decline in order intake.
  5. FY2020-Q1AdvancedAnnual report

    「Although orders increased for safety measure construction work at nuclear power plants, in addition to increases in construction work for cogeneration facilities and solar power generation facilities, among others,」

    The increase in construction work for cogeneration facilities was cited as a factor affecting the change in order intake in the first quarter.
  6. FY2019RestatedAnnual report

    「We worked to increase orders and sales in the inspection and maintenance of thermal, nuclear and hydroelectric power plants; decommissioning-related work at the Fukushima Daiichi Nuclear Power Station and Fukushima reconstruction-related operations; safety measure construction work at nuclear power plants; and construction work for large-scale thermal power generation facilities, cogeneration facilities, communications facilities and large-scale solar power generation facilities, among others, while working across the entire company to generate profit.」

    Construction work for cogeneration facilities has continued alongside construction work for large-scale thermal power, communications and solar power facilities, among others.
  7. FY2019-Q3RestatedAnnual report

    「The company expanded its work in large-scale thermal power generation facilities, cogeneration facilities, large-scale solar power generation facilities and other areas, making a group-wide effort to generate profit.」

    Construction work for cogeneration facilities continues as a specific business area.
  8. FY2019-Q2RestatedAnnual report

    「Specifically, the Group sought to expand its business and made every effort to generate profits through inspection and maintenance of thermal, nuclear and hydroelectric power plants, decommissioning-related work at Fukushima Daiichi Nuclear Power Station and reconstruction-related work in Fukushima, safety-related work at nuclear power plants, and work involving large-scale thermal power generation facilities, cogeneration and large-scale solar power generation facilities.」

    Cogeneration (combined heat and power)-related construction work continues as a specific business area.
  9. FY2019-Q1RestatedAnnual report

    「In addition, across areas including power generation equipment-related construction at petrochemical plants, cogeneration-related construction, and large-scale solar power generation facility installation, the entire Group worked to secure and expand orders and sales and generate profits.」

    Cogeneration-related construction work continues to be listed as a specific area of focus within power generation facility-related construction work.
  10. FY2018-Q3RestatedAnnual report

    「Cogeneration-related construction work」

    Cogeneration-related construction work continues to be listed as a specific area of focus within power generation facility-related construction work.
  11. FY2018-Q2First statedAnnual report

    「Cogeneration-related construction work」

    Cogeneration-related construction work is newly specified as a specific area of focus within power generation facility-related construction work.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
Tokyo Energy & Systems's next results are scheduled for 2026-11-05. Read the earnings preview
News