Hokuriku Electrical Construction (1930) · InitiativeAdvanced
Construction of a small hydropower plant
First written in FY2021. 2 of 3 entries say "Advanced", first in FY2022. Latest entry: FY2023.
3entries
3years
0from disclosures
How it moved
Same theme, other companies
Commercialization of New Businesses Based on Water ResourcesA theme 6 companies write about · 3 as a headwind · 3 as a tailwind
1 other company's latest entry also says "Advanced".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2023AdvancedAnnual report
「The Company is constructing its first small hydroelectric power plant in the Kimoto district of Ono, Fukui Prefecture.」
投資予定額は1,149百万円、既支払額は1,124百万円となり、運転開始予定は2023年4月へ更新された。建設完了・運転開始前の段階として記載されている。 - FY2022AdvancedAnnual report
「The Company is constructing its first small hydroelectric power plant in the Kimoto district of Ono, Fukui Prefecture.」
小水力発電所の投資予定額1,100百万円に対し既支払額は803百万円となり、2022年7月の運転開始予定と計画が更新された。 - FY2021First statedAnnual report
「The Company is constructing its first small hydroelectric power plant in the Kimoto district of Ono, Fukui Prefecture.」
The Company is constructing its first small hydroelectric power plant. Total planned investment is ¥1,100 million, with ¥70 million already paid. Construction began in November 2020, completion was scheduled for June 2022, and funding was to come from internal sources.