Uncertainty in Estimating Total Construction Costs
First written in FY2021. 4 of 5 entries say "Restated". Latest entry: FY2025.
The whole theme swung hardest in 2022: 9 of 86 companies on the "Worse" side.
52 other companies' latest entry also says "Restated".
- FY2025RestatedAnnual report
「The key estimate in recognizing revenue from construction contracts whose performance obligations are satisfied over time is the stage of completion, and the key assumption underlying the stage of completion is a reasonable estimate of total construction costs.」
The uncertainty surrounding the stage of completion and estimates of total construction costs continues to be disclosed, and revenue from completed construction contracts for the current fiscal year amounted to ¥3,047.3 million. - FY2024-Q3RestatedAnnual report
「During the nine-month period of the current fiscal year, there were no material changes in the occurrence of major risks that management recognizes could materially affect the consolidated companies' financial condition, operating results or cash flows, among the matters related to the business and accounting described in the quarterly securities report, or in the "Business and Other Risks" described in the securities report for the previous fiscal year.」
The Company states that there have been no significant changes to its existing key risks, including uncertainty surrounding estimates of total construction costs. - FY2023RestatedAnnual report
「The key estimate in recognizing revenue from construction contracts whose performance obligations are satisfied over time is the stage of completion, and the key assumption underlying the stage of completion is a reasonable estimate of total construction costs.」
The uncertainty surrounding the stage of completion and estimates of total construction costs continues to be disclosed as a significant accounting estimate relating to ¥28,806 million in revenue from completed construction contracts. - FY2022RestatedAnnual report
「The key estimate in recognizing revenue from construction contracts whose performance obligations are satisfied over time is the stage of completion, and the key assumption underlying the stage of completion is a reasonable estimate of total construction costs.」
The uncertainty surrounding estimates of total construction costs continues to be disclosed, and revenue from completed construction contracts recognized over time during the current fiscal year amounted to ¥29,829 million. - FY2021First statedAnnual report
「Current consolidated fiscal year Net sales from completed construction contracts 17,407 Because construction projects are generally long-term, estimated total construction costs may differ from actual construction costs incurred if design or specification changes, construction delays, cost-reduction activities, or changes in construction material and labor unit costs due to market conditions occur during the course of construction. This could have a material impact on revenue recognized under the percentage-of-completion method in the consolidated financial statements for the following consolidated fiscal year.」
For ¥17,407 million in revenue from completed construction contracts recognized under the percentage-of-completion method, the estimate of total construction costs is a key assumption, and the disclosure identifies as a new accounting risk the possibility of a material impact on revenue in the following fiscal year due to specification changes, construction delays and changes in material and labor unit costs.