- FY2026AdvancedAnnual report
「In addition, although the U.S. subsidiary lost a contract for environmental protection work at an aging dam, the fourth work section of the ground improvement project at an LNG processing plant site was ordered ahead of schedule, enabling the company to exceed the plan.」
For overseas construction projects through the U.S. base, the fourth work section of the ground improvement project at an LNG processing plant site was ordered ahead of schedule, resulting in performance above plan. - FY2026-H1AdvancedAnnual report
「Meanwhile, at the U.S. subsidiary, the ground improvement work at an LNG processing plant site, which had contributed significantly to the previous fiscal year's results, was temporarily completed. Testing for additional work has now been completed, and detailed design and the construction plan are being prepared, with the main construction work expected to begin in December.」
For the U.S. subsidiary's large-scale LNG project, testing for additional work has been completed, work has progressed to the preparation of detailed design and the construction plan, and the main construction work is expected to begin in December. - FY2025-H1AdvancedAnnual report
「Meanwhile, at the U.S. subsidiary, the large-scale ground improvement project at an LNG processing plant site, carried over from the previous fiscal year, progressed smoothly,」
The company reported concrete progress in its initiative to use the United States as a base for entering the overseas construction market, with ground improvement work at an LNG processing plant site progressing smoothly. - FY2024AdvancedAnnual report
「In addition, the U.S. subsidiary significantly exceeded the plan by winning large-scale contracts for ground improvement work at an LNG processing plant site and for dam ground improvement work.」
Under its policy of using the U.S. subsidiary as a base for entering the overseas construction market, the company won large-scale contracts for ground improvement work at an LNG processing plant site and a dam. - FY2022RestatedAnnual report
「JAFEC USA, Inc., a consolidated subsidiary, was established in Nevada, United States, in October 2009 as a base for entering the overseas construction market,」
The company continues to position its U.S. subsidiary as a base for entering the overseas construction market. - FY2017RestatedAnnual report
「The group established a subsidiary in the United States as a base for entering the overseas construction market in the future.」
The company continues to position its U.S. subsidiary as a base for entering the overseas construction market. However, profitability on U.S. construction projects deteriorated during the fiscal year and became an issue. - FY2016First statedAnnual report
「The group established a subsidiary in the United States as a base for entering the overseas construction market in the future.」
The company has established its U.S. subsidiary, JAFEC USA, Inc., as a base for entering the overseas construction market.