Delays and Cost Increases Due to Changes in Construction Methods and Unexpected Geological Conditions on a U.S. Construction Project

First written in FY2017-Q2. 11 of 30 entries say "Restated". Latest entry: FY2026.

30entries
11years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseMitigatedFY2024 – FY20262016: 12017: 420172018: 420182019: 320192020: 320202021: 320212022: 420222023: 320232024: 320242025: 120252026: 12026
Same theme, other companies
Delays and cost increases in U.S. LNG construction due to construction methods and geological issuesA theme 1 companies write about · 1 as a headwind · 0 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2026MitigatedAnnual report

    「Net sales in Japan exceeded the plan as orders increased. Meanwhile, at the U.S. subsidiary, full-scale construction began in December following the early placement of orders for Train 4 (Section 4) of the ground-improvement project at the LNG refinery plant site, which had made a significant contribution to results in the previous period. However, most of the work consisted of detailed design and trial construction, resulting in a figure below the previous-period result.」

    Full-scale construction for Section 4 of the LNG project began in December, progressing beyond detailed design and trial construction. The disclosure also states that the result was below the previous period because most of the work consisted of design and trial construction.
  2. FY2026-H1MitigatedAnnual report

    「Trial construction for the additional work has now been completed, and detailed design and preparation of the construction plan are under way. Full-scale construction is expected to begin in December.」

    Rather than the previous construction delays and interruptions, the disclosure describes the completion of trial construction for additional work and the preparation of detailed designs and plans for full-scale construction.
  3. FY2025-H1MitigatedAnnual report

    「The major ground-improvement project at the LNG refinery plant site, carried over from the previous period, progressed smoothly」

    Regarding the risk of delays and costs incurred ahead of revenue on U.S. projects, the company explained that the major carryover project progressed smoothly, indicating an improvement from the previous construction delays.
  4. FY2024MitigatedAnnual report

    「At the U.S. subsidiary as well, results were broadly in line with the plan, as the major ground-improvement project at the LNG refinery plant site progressed smoothly and ground-improvement work on the dam also commenced.」

    The company explained that, in contrast to the previous construction interruptions and indirect costs incurred ahead of revenue, the ground-improvement project at the LNG refinery plant site progressed smoothly and ground-improvement work on the dam also commenced.
  5. FY2024-Q3RestatedAnnual report

    「Meanwhile, at JAFEC USA,Inc., the U.S. subsidiary, the amount of the loss declined because of test construction for the ground improvement project at an LNG processing plant site,」

    The company explained that, although profitability issues related to U.S. projects continue, the loss was reduced through trial ground-improvement construction at the LNG refinery plant site.
  6. FY2024-Q2MitigatedAnnual report

    「Meanwhile, at JAFEC USA,Inc., the U.S. subsidiary, the size of the loss was substantially reduced as work began on trial ground-improvement construction at the LNG refinery plant site, resulting in consolidated ordinary income of ¥649 million, up ¥151 million from the same quarter of the previous year, and quarterly net income attributable to owners of the parent of ¥416 million, up ¥132 million.」

    The company explained that the loss at JAFEC USA was substantially reduced after trial ground-improvement construction began at the LNG refinery plant site.
  7. FY2024-Q1MitigatedAnnual report

    「Meanwhile, at JAFEC USA,Inc., the U.S. subsidiary, carryover projects from the previous period progressed smoothly, resulting in consolidated ordinary income of ¥389 million, up ¥174 million from the same quarter of the previous year, and quarterly net income attributable to owners of the parent of ¥274 million, up ¥165 million.」

    The company explained that carryover projects from the previous period progressed smoothly at the U.S. subsidiary, increasing consolidated ordinary income and quarterly net income attributable to owners of the parent from the same period of the previous year.
  8. FY2023-Q3RestatedAnnual report

    「However, at JAFEC USA,Inc., the U.S. subsidiary, construction on the planned large-scale project continued to be suspended for ecological and environmental protection reasons, causing indirect costs to be incurred ahead of schedule,」

    At the U.S. subsidiary, interruptions to major construction projects for ecosystem and environmental protection and indirect costs incurred ahead of revenue continue.
  9. FY2023-Q2RestatedAnnual report

    「However, construction interruptions for ecosystem and environmental protection continued at JAFEC USA,Inc., the U.S. subsidiary, causing indirect costs to be incurred ahead of revenue,」

    At JAFEC USA, construction interruptions for ecosystem and environmental protection and indirect costs incurred ahead of revenue continue.
  10. FY2023-Q1ReframedAnnual report

    「However, at JAFEC USA,Inc., the U.S. subsidiary, indirect costs were incurred ahead of schedule because construction was suspended for ecological and environmental protection reasons,」

    Regarding the issues affecting U.S. projects, construction interruptions for ecosystem and environmental protection and indirect costs incurred ahead of revenue are cited as factors, in addition to the previous changes in construction methods, unforeseen geological conditions, and delays caused by infectious diseases and natural disasters.
  11. FY2022WorsenedAnnual report

    「Meanwhile, at the local US subsidiary, construction of ground improvements for an LNG terminal was postponed due in part to the impact of carbon-neutral policies. In addition, construction commencement was substantially delayed for some projects due to ecological and environmental issues involving protected plants, resulting in performance well below plan.」

    Regarding U.S. projects, in addition to the previous construction interruptions and delays in progress, LNG projects were postponed due to the carbon-neutrality policy, and major delays in starting construction occurred due to issues involving protected plants.
  12. FY2022-Q3WorsenedAnnual report

    「Meanwhile, at the U.S. subsidiary, construction profitability deteriorated because of work stoppages caused by natural disasters and the novel coronavirus disease, but the company reduced indirect expenses and yard costs and reviewed its staffing, maintaining its initial operating profit plan.」

    The company explained that, in addition to the previous delays in construction progress and costs incurred ahead of revenue, construction interruptions caused by natural disasters and infectious diseases worsened project profitability. Meanwhile, the operating income plan was maintained through cost reductions and a review of staffing.
  13. FY2022-Q2MitigatedAnnual report

    「Meanwhile, at the U.S. subsidiary, construction volume remained sluggish because of work stoppages caused by natural disasters and other factors, but the company maintained its plan for profit by reducing indirect costs and other expenses.」

    The company explained that, although construction interruptions due to natural disasters and other factors continued at the U.S. subsidiary, the plan was maintained in terms of earnings through reductions in indirect costs and other expenses.
  14. FY2022-Q1RestatedAnnual report

    「Because indirect costs and other expenses were incurred ahead of revenue at JAFEC USA,Inc., the consolidated ordinary loss was ¥4 million」

    Indirect costs and other expenses incurred ahead of revenue at JAFEC USA continue to be cited as a factor behind the deterioration in consolidated results.
  15. FY2021-Q3WorsenedAnnual report

    「Meanwhile, at the U.S. subsidiary, earnings fell significantly below expectations as construction delays caused by the impact of the coronavirus disease led to higher construction overhead costs.」

    The company explained that, at JAFEC USA, substantial delays in construction progress caused by the impact of infectious diseases and higher indirect construction costs caused earnings to fall significantly short of expectations.
  16. FY2021-Q2WorsenedAnnual report

    「At the U.S. subsidiary, earnings fell significantly short of expectations due to substantial delays in construction progress and increased indirect construction costs.」

    The company explained that, at JAFEC USA, in addition to the previous delays in construction progress and costs incurred ahead of revenue, substantial delays in construction progress and higher indirect construction costs caused earnings to fall significantly short of expectations.
  17. FY2021-Q1WorsenedAnnual report

    「This was because JAFEC USA,Inc., the U.S. subsidiary, had no completed construction work at active sites.」

    Regarding the U.S. subsidiary, the company explained that, in addition to the previously reported delays in construction progress and costs incurred ahead of revenue, no construction work was completed at active sites in the first quarter.
  18. FY2020MitigatedAnnual report

    「In addition to focusing orders on profitability, reviewing its construction structure, and cutting selling, general and administrative expenses, the U.S. subsidiary also benefited from collecting previously unpaid construction payments, reducing the amount of its loss.」

    The company explained that, in response to the previous issues of construction delays and costs incurred ahead of revenue on U.S. projects, the loss was reduced through orders focused on profitability, a review of the construction structure, cuts in general and administrative expenses, and collection of outstanding construction payments.
  19. FY2020-Q2MitigatedAnnual report

    「At the U.S. subsidiary, progress in collecting construction payments following changes in contract terms contributed to a reduction in the size of the loss.」

    The company explained that, although issues at the U.S. subsidiary remain, the size of the loss narrowed as collection of construction payments following changes in contract terms progressed.
  20. FY2020-Q1RestatedAnnual report

    「However, partly because indirect costs and other expenses were incurred ahead of revenue due to delays in mobilizing for construction and other factors at JAFEC USA,Inc., ordinary income was ¥204 million, up ¥5 million from the same quarter of the previous year, and quarterly net income attributable to owners of the parent was ¥100 million, up ¥9 million.」

    The company explained that indirect costs and other expenses were incurred ahead of revenue at JAFEC USA due to delays in mobilizing for construction and other factors, indicating that issues involving delays on U.S. projects and costs incurred ahead of revenue continue. Meanwhile, consolidated ordinary income and quarterly net income attributable to owners of the parent exceeded the same quarter of the previous year.
  21. FY2019MitigatedAnnual report

    「At the U.S. subsidiary, the company worked to reduce the size of its loss by focusing orders on profitability, reviewing its construction structure, and cutting selling, general and administrative expenses.」

    The company explained that, although profitability and progress issues remain on U.S. projects, it sought to reduce the loss by prioritizing profitable orders, reviewing its construction structure, and cutting general and administrative expenses.
  22. FY2019-Q2RestatedAnnual report

    「However, because indirect costs and other expenses were incurred ahead of revenue at JAFEC USA,Inc., quarterly net income attributable to owners of the parent was a loss of ¥17 million, compared with income of ¥20 million in the same quarter of the previous year.」

    Indirect costs and other expenses incurred ahead of revenue at JAFEC USA continue to be cited as a factor behind the quarterly net loss attributable to owners of the parent for the cumulative consolidated period through the second quarter.
  23. FY2019-Q1ReframedAnnual report

    「Although solid orders and construction progress at domestic branches generated ordinary income of ¥198 million, indirect costs and other expenses were incurred ahead of revenue at JAFEC USA,Inc., resulting in quarterly net income attributable to owners of the parent of ¥90 million, compared with a net loss of ¥77 million in the same quarter of the previous year.」

    In addition to the previously cited changes in construction methods, unforeseen geological conditions, and delays in construction progress, the company cited indirect costs and other expenses incurred ahead of revenue as a factor in the U.S. subsidiary's operating performance this quarter.
  24. FY2018RestatedAnnual report

    「However, the U.S. subsidiary was forced to accept a significant decline due to delays in starting major construction projects and other factors.」

    Delays in starting major construction projects at JAFEC USA continued and were cited as a factor behind the decline in completed construction revenue.
  25. FY2018-Q3RestatedAnnual report

    「Progress on projects in hand at domestic branches exceeded expectations, resulting in net sales of ¥16,847 million, up ¥2,114 million from the same quarter of the previous year. In terms of earnings, despite delays in construction progress at JAFEC USA, the U.S. subsidiary, increased profits at domestic branches and subsidiaries resulted in operating income of ¥317 million, compared with an operating loss of ¥443 million in the same quarter of the previous year, and ordinary income of ¥443 million, compared with an ordinary loss of ¥270 million, representing a significant improvement.」

    Although delays in construction progress at JAFEC USA continued to occur, consolidated results improved from the same period of the previous year due to increased profits at domestic branches and subsidiaries.
  26. FY2018-Q2RestatedAnnual report

    「Although construction progress was delayed at JAFEC USA,Inc., the U.S. subsidiary, solid construction progress in Japan contributed to operating income of ¥174 million, compared with an operating loss of ¥452 million in the same quarter of the previous year,」

    The company explained that delays in construction progress at JAFEC USA also occurred during the cumulative period through the second quarter. Meanwhile, solid construction progress in Japan improved operating results from a loss in the same period of the previous year to a profit.
  27. FY2018-Q1RestatedAnnual report

    「On a non-consolidated basis, although ¥305 million in ordinary income was recorded due to solid orders and construction progress, delays in construction progress at JAFEC USA,Inc., the U.S. subsidiary, resulted in an operating loss of ¥12 million, compared with a loss of ¥182 million in the same quarter of the previous year,」

    Delays in construction progress at JAFEC USA continue to be a factor behind the operating loss in the first quarter. The operating loss narrowed from the same quarter of the previous year, but no new resolution of the delays themselves was reported.
  28. FY2017WorsenedAnnual report

    「Due to the effects of construction delays caused by changes in construction methods and unforeseen geological issues, as well as delays in final settlement, at projects undertaken by the U.S. subsidiary, operating results were an operating loss of ¥305 million.」

    In addition to higher costs caused by changes in construction methods, unforeseen geological conditions, and delays on U.S. projects, delays in final settlement are also cited as factors behind the full-year loss, following the second and third quarters.
  29. FY2017-Q3RestatedAnnual report

    「However, due to higher costs resulting from changes in construction methods and construction delays caused by unforeseen geological issues at projects undertaken by the U.S. subsidiary, net sales were ¥14,732 million, down ¥2,332 million from the same quarter of the previous year; the company recorded an operating loss of ¥443 million, compared with operating income of ¥1,156 million in the same quarter of the previous year; an ordinary loss of ¥270 million, compared with ordinary income of ¥1,262 million; and a quarterly net loss attributable to owners of the parent of ¥510 million, compared with net income of ¥813 million.」

    Delays and higher costs at projects undertaken by the U.S. subsidiary, caused by changes in construction methods and unforeseen geological issues, continue to be cited as factors behind losses in the cumulative consolidated period through the third quarter.
  30. FY2017-Q2First statedAnnual report

    「Higher costs resulting from construction delays caused by changes in construction methods and unforeseen geological issues at projects undertaken by the U.S. subsidiary」

    The company explained that changes in construction methods and construction delays caused by unforeseen geological issues at projects undertaken by the U.S. subsidiary affected actual cumulative results for the second quarter.
Moved together

"JAFEC USA Earnings Recovery" moved the same way as this thread, in the same document, in 13 of its 30 moves.

1398887★123456
  1. ★This thread
  2. 1JAFEC USA Earnings Recovery13×
  3. 2Higher equity ratio9×
  4. 3Expansion of Construction Capabilities and Equipment8×
  5. 4Share Repurchases as an Agile Capital Policy8×
  6. 5Cumulative second-quarter revenue decline, operating loss, ordinary loss and net loss8×
  7. 6Recognition of Foreign-Exchange Losses7×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.