Nankai Tatsumura Construction (1850) · RiskAchieved

Litigation against 大覚 for construction contract payments and damages for defects

First written in FY2016. 9 of 16 entries say "Restated". Latest entry: FY2020.

16entries
5years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2016 – FY2017RestatedFY2018-Q2 – FY2019-Q2WorsenedFY2020-Q1 – FY2020-Q32016: 320162017: 420172018: 420182019: 320192020: 22020
Same theme, other companies

The whole theme swung hardest in 2025: 12 of 70 companies on the "Worse" side.

6 other companies' latest entry also says "Achieved".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 183 companies compared. The sentences above are computed from all 183.
Full recordFilings, disclosures and news, newest first
  1. FY2020AchievedAnnual report

    「The Company had filed a petition with the Supreme Court to accept its appeal on 22 April 2019, but was notified on 3 March 2020 of the Supreme Court's decision not to accept the appeal. As a result, the Osaka High Court judgment ordering the Company to pay damages to 大覚 became final. In March 2020, the Company paid a total of ¥2,756 million, comprising the ¥2,664 million provision for litigation losses recognized in the previous consolidated fiscal year and ¥92 million in default damages recognized as an extraordinary loss in the current consolidated fiscal year, bringing the litigation to an end.」

    The Supreme Court decided not to accept the appeal, and the litigation ended after payment of ¥2,756 million in damages and other amounts.
  2. FY2020-Q3WorsenedAnnual report

    「Provision for litigation losses - 73」

    The Company recognized ¥73 million in provision for litigation losses relating to the litigation with 大覚, increasing the provision for litigation losses from ¥2,664 million at the end of the previous consolidated fiscal year to ¥2,737 million.
  3. FY2020-Q2WorsenedAnnual report

    「Provision for litigation losses - 46」

    The Company recognized ¥46 million in provision for litigation losses relating to the litigation with 大覚, increasing the provision for litigation losses from ¥2,664 million at the end of the previous consolidated fiscal year to ¥2,710 million.
  4. FY2020-Q1MaterialisedAnnual report

    「Subsequently, 大覚 appealed the first-instance judgment to the Osaka High Court on 11 March 2013. On 12 April 2019, the Osaka High Court issued a judgment ordering the Company to pay 大覚 ¥1,356 million in damages, ¥519 million received from the foreclosure sale of real property owned by 大覚 pursuant to the provisional enforcement declaration attached to the first-instance judgment, and default damages on each of these amounts. The Company considers the judgment unacceptable and, on 22 April 2019, filed a petition with the Supreme Court to accept its appeal. Although the Company is confident that its arguments are justified, it has recognized a reasonably calculated amount based on the second-instance judgment as a provision for litigation losses from the standpoint of maintaining financial soundness.」

    The appellate judgment was issued, ordering payment of damages and other amounts. The Company filed a petition with the Supreme Court to accept its appeal while recognizing the amount based on the second-instance judgment as a provision for litigation losses.
  5. FY2019-Q3AdvancedAnnual report

    「Subsequently, 大覚 appealed the first-instance judgment to the Osaka High Court on 11 March 2013, seeking ¥3,459 million. On 23 May 2017, it filed a motion in the appellate proceedings to amend the relief sought, changing the damages claimed from the Company to ¥6,041 million as its primary claim and ¥6,199 million as its alternative claim. It also sought ¥2,938 million in damages that it alleged it incurred when the Company conducted foreclosure proceedings against real property owned by 大覚 pursuant to the provisional enforcement declaration attached to the first-instance judgment. The appellate proceedings have now been concluded. Judgment is scheduled for 12 April 2019.」

    The appellate proceedings involving 大覚 have concluded, and judgment was scheduled for 12 April 2019. The details of the dispute, including the amended and additional claims, remain as previously stated.
  6. FY2019-Q2RestatedAnnual report

    「Subsequently, 大覚 appealed the first-instance judgment to the Osaka High Court on 11 March 2013, seeking ¥3,459 million, and the appeal remains pending. On 23 May 2017, 大覚 filed a motion in the appellate proceedings to amend the relief sought, changing the damages claimed from the Company to ¥6,041 million as its primary claim and ¥6,199 million as its alternative claim. It is also seeking ¥2,938 million in damages that it alleges it incurred when the Company conducted foreclosure proceedings against real property owned by 大覚 pursuant to the provisional enforcement declaration attached to the first-instance judgment. The Company will continue to pursue the appeal so that its arguments are accepted by the appellate court.」

    The Company continues to disclose the status and response policy regarding the pending appeal, the amendment of the claims to ¥6,041 million and ¥6,199 million, and the additional claim for ¥2,938 million.
  7. FY2019-Q1RestatedAnnual report

    「In addition, on 23 May 2017, 大覚 filed a motion to amend the relief sought in the appellate proceedings, increasing its damages claim against the company to ¥6,041 million as its primary claim and ¥6,199 million as its alternative claim. It is also seeking ¥2,938 million in damages that it alleges it incurred as a result of the company initiating foreclosure proceedings against real estate owned by 大覚 based on the declaration of provisional execution in the first-instance judgment. The company intends to continue responding in the appellate proceedings so that its arguments will also be upheld on appeal.」

    It continues to disclose the previous status of the pending appellate proceedings, the change in the amount claimed to ¥6,041 million and ¥6,199 million, and the additional claim of ¥2,938 million.
  8. FY2018RestatedAnnual report

    「The appellate proceedings remain pending. In addition, on 23 May 2017, 大覚 filed a motion to amend the relief sought in the appellate proceedings, increasing its damages claim against the company to ¥6,041 million as its primary claim and ¥6,199 million as its alternative claim. It is also seeking ¥2,938 million in damages that it alleges it incurred as a result of the company initiating foreclosure proceedings against real estate owned by 大覚 based on the declaration of provisional execution in the first-instance judgment.」

    It continues to disclose the pending appellate proceedings, the change in the amount claimed, and the additional claim.
  9. FY2018-Q3RestatedAnnual report

    「大覚 subsequently appealed the first-instance judgment to the Osaka High Court on 11 March 2013, with a claim of ¥3,459 million, and the appellate proceedings remain pending. In addition, on 23 May 2017, 大覚 filed a motion to amend the relief sought in the appellate proceedings, increasing its damages claim against the company to ¥6,041 million as its primary claim and ¥6,199 million as its alternative claim. It is also seeking ¥2,938 million in damages that it alleges it incurred as a result of the company initiating foreclosure proceedings against real estate owned by 大覚 based on the declaration of provisional execution in the first-instance judgment. The company intends to continue responding in the appellate proceedings so that its arguments will also be upheld on appeal.」

    The appellate proceedings remain pending, and the previous status, including the changes in the amount claimed and the additional claim, is restated.
  10. FY2018-Q2RestatedAnnual report

    「In addition, on 23 May 2017, 大覚 filed a motion to amend the relief sought in the appellate proceedings, increasing its damages claim against the company to ¥6,041 million as its primary claim and ¥6,199 million as its alternative claim. It is also seeking ¥2,938 million in damages that it alleges it incurred as a result of the company initiating foreclosure proceedings against real estate owned by 大覚 based on the declaration of provisional execution in the first-instance judgment.」

    The pending appellate proceedings, changes in the amount claimed, and additional claims are restated as having remained unchanged from the previous quarter.
  11. FY2018-Q1WorsenedAnnual report

    「大覚 subsequently appealed the first-instance judgment to the Osaka High Court on 11 March 2013, with a claim of ¥3,459 million, and the appellate proceedings remain pending. In addition, on 23 May 2017, 大覚 filed a motion to amend the relief sought in the appellate proceedings, increasing its damages claim against the company to ¥6,041 million as its primary claim and ¥6,199 million as its alternative claim. It is also seeking ¥2,938 million in damages that it alleges it incurred as a result of the company initiating foreclosure proceedings against real estate owned by 大覚 based on the declaration of provisional execution in the first-instance judgment.」

    While the appellate proceedings were pending, the opposing party amended the relief sought, increasing the previous claim of ¥3,459 million to ¥6,041 million as its primary claim and ¥6,199 million as its alternative claim, and adding a claim for ¥2,938 million in damages.
  12. FY2017RestatedAnnual report

    「However, on 11 March 2013, 大覚 appealed the first-instance judgment to the Osaka High Court. The company intends to continue responding in the appellate proceedings so that its arguments will also be upheld on appeal.」

    The company continues to respond to the appellate proceedings following the first-instance judgment. No new change in the amount claimed or the judgment has been indicated.
  13. FY2017-Q3RestatedAnnual report

    「The company filed an action with the Osaka District Court on 7 January 2010 seeking payment of the outstanding ¥1,581 million in construction contract consideration for the condominium project “Otsukyo Station Place,” which it had undertaken from 大覚 Co., Ltd. (hereinafter, “大覚”). Meanwhile, 大覚 had filed an action against the company seeking damages totaling ¥3,791 million, alleging that the property contained major defects. The two actions were consolidated and heard together through court proceedings, and the Osaka District Court handed down its first-instance judgment on 26 February 2013. The judgment largely upheld the company’s claim against 大覚 for construction contract consideration, excluding approximately ¥10 million in repair costs and other amounts, while dismissing 大覚’s claim. However, on 11 March 2013, 大覚 appealed the first-instance judgment to the Osaka High Court. The company will continue to respond in the appellate proceedings so that its arguments will also be upheld on appeal.」

    The amounts claimed, the first-instance judgment, and the policy for responding to the appellate proceedings are restated unchanged.
  14. FY2017-Q2RestatedAnnual report

    「The company filed an action with the Osaka District Court on 7 January 2010 seeking payment of the outstanding ¥1,581 million in construction contract consideration for the condominium project “Otsukyo Station Place,” which it had undertaken from 大覚 Co., Ltd. (hereinafter, “大覚”). Meanwhile, 大覚 had filed an action against the company seeking damages totaling ¥3,791 million, alleging that the property contained major defects. The two actions were consolidated and heard together through court proceedings, and the Osaka District Court handed down its first-instance judgment on 26 February 2013. The judgment largely upheld the company’s claim against 大覚 for construction contract consideration, excluding approximately ¥10 million in repair costs and other amounts, while dismissing 大覚’s claim. However, on 11 March 2013, 大覚 appealed the first-instance judgment to the Osaka High Court. The company will continue to respond in the appellate proceedings so that its arguments will also be upheld on appeal.」

    The company continues to respond to the appellate proceedings following the first-instance judgment. No material change in the amount claimed or the status of the litigation has been indicated.
  15. FY2017-Q1RestatedAnnual report

    「The company filed an action with the Osaka District Court on 7 January 2010 seeking payment of the outstanding ¥1,581 million in construction contract consideration for the condominium project “Otsukyo Station Place,” which it had undertaken from 大覚 Co., Ltd. (hereinafter, “大覚”). Meanwhile, 大覚 had filed an action against the company seeking damages totaling ¥3,791 million, alleging that the property contained major defects. The two actions were consolidated and heard together through court proceedings, and the Osaka District Court handed down its first-instance judgment on 26 February 2013. The judgment largely upheld the company’s claim against 大覚 for construction contract consideration, excluding approximately ¥10 million in repair costs and other amounts, while dismissing 大覚’s claim. However, on 11 March 2013, 大覚 appealed the first-instance judgment to the Osaka High Court. The company will continue to respond in the appellate proceedings so that its arguments will also be upheld on appeal.」

    The company continues to respond to the appellate proceedings following the first-instance judgment. No material change in the amount claimed or the status of the litigation has been indicated.
  16. FY2016First statedAnnual report

    「The company filed an action with the Osaka District Court on 7 January 2010 seeking payment of the outstanding ¥1,581 million in construction contract consideration for the condominium project “Otsukyo Station Place,” which it had undertaken from 大覚 Co., Ltd. (hereinafter, “大覚”). Meanwhile, 大覚 had filed an action against the company seeking damages totaling ¥3,791 million, alleging that the property contained major defects.」

    大覚 continued to appeal after the first-instance judgment, and the company stated that it would continue responding to the appellate proceedings.
Moved together

"Guarantee obligations related to customer advances" moved the same way as this thread, in the same document, in 4 of its 16 moves.

422★123
  1. ★This thread
  2. 1Guarantee obligations related to customer advances4×
  3. 2Decline in Assets and Liabilities and Increase in Net Assets2×
  4. 3Market Price Risk on Investment Securities2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Nankai Tatsumura Construction's next results are scheduled for 2026-10-30. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.