Explosion at the Ishikari Bio Energy Power Generation Facility and Suspension of Commercial Operations
First written in FY2025-H1. 5 of 7 entries say "Mitigated", first in FY2026-H1. Latest entry: 2026-09-03.
No other company in this theme has enough history to compare yet.
- FY2026MitigatedAnnual report
「復旧及び再発防止に係る設備改造工事が当初計画どおり完了し、2026年4月から商業運転を再開しています。」
爆発事故後に停止していた商業運転が、復旧・再発防止工事の完了を経て2026年4月から再開したと記載しています。 - 2026-05-15MitigatedEarnings
「Commercial operations had been suspended since the explosion at the power generation facility, but equipment modification work for restoration and the prevention of recurrence was completed as originally planned, and commercial operations resumed in April 2026.」
The facility progressed from the suspension of commercial operations following the explosion to completion of restoration and recurrence-prevention work and the resumption of commercial operations. - FY2026-H1MitigatedAnnual report
「復旧及び再発防止に係る設備改造工事を一部完了したこと等により、2025年9月28日から試運転を開始しています。今後は、発電施設のうちボイラー内の配管交換作業を実施するため再度運転を停止しますが、復旧及び再発防止に係る設備改造工事は当初計画どおり進捗しており、2026年4月から本格的な商業運転を再開する予定です。」
爆発事故後に停止していた商業運転について、復旧・再発防止工事の一部完了と試運転開始まで進展しました。ただし、配管交換のため再度停止予定であり、本格的な商業運転は2026年4月再開予定です。 - FY2025爆発事故に伴う減損損失と再稼働計画の開示Annual report
「上記の減損損失は、同社が保有する資産及び同社を取得した際に計上したのれんについて、同社の発電施設で発生した爆発事故に伴う収益性の低下により、関連する資産及びのれんの帳簿価額を回収可能価額まで減額した結果、当該減少額を特別損失に計上したものです。」
爆発事故に伴う減損損失13,234百万円(発電設備12,915百万円、のれん319百万円)を計上しました。一方、事故調査と再発防止策を踏まえ、再稼働に向けた取り組みを継続し、長期的には採算がとれる事業と見込む旨を記載しています。 - FY2025-H1MaterialisedAnnual report
「また、2024年7月19日に当社の連結子会社である石狩バイオエナジー合同会社が運営する発電施設において発生した爆発事故に起因する商業運転の停止により、同社が適用していた為替予約にかかるヘッジ会計を中止したことに伴い、営業外費用に為替予約評価損を計上したこと等により、経常損失は3,101百万円(前年同期間は7,180百万円の経常利益)となりました。」
2024年7月19日に発電施設の爆発事故が発生し、商業運転が停止しました。これに伴い為替予約のヘッジ会計を中止し、為替予約評価損3,908百万円を営業外費用に計上したほか、投資開発事業にも売上高減少・調査費用・維持管理費用の影響が生じています。