Okumura (1833) · RiskMaterialised
Recognition of Substantial Losses on a Specific Large-Scale Civil Engineering Project
First written in FY2025-H1. 2 of 2 entries say "Materialised", first in FY2025-H1. Latest entry: FY2025.
2entries
1years
0from disclosures
How it moved
Same theme, other companies
Cost, Schedule and Profitability Risk in Construction Contracting ProjectsA theme 35 companies write about · 35 as a headwind · 0 as a tailwind
Okumura moved to the "Worse" side of this theme in 2025, 4 years after the typical company in this theme (2021).
The whole theme swung hardest in 2021: 11 of 25 companies on the "Worse" side.
7 other companies' latest entry also says "Materialised".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 35 companies compared. The sentences above are computed from all 35.Full recordFilings, disclosures and news, newest first
- FY2025MaterialisedAnnual report
「建築事業の売上総利益は、売上高が増加したことに加え、大型で高採算の工事が竣工したこと等により前期に比べ増加した一方で、土木事業の同利益は、特定の国内大型工事が建設資機材価格や労務費の高騰等により見積総原価が増大し、損益改善の見通しが立たないため多額の工事損失引当金を計上したこと等が影響し、前期に比べ減少となりました。」
特定の国内大型土木工事について、施工方法変更、施工効率悪化、天候不順、資材価格・労務費高騰等により損失が発生し、工事損失引当金繰入額2,337百万円を計上しました。 - FY2025-H1MaterialisedAnnual report
「特定の国内大型工事において、当初計画していた施工方法の変更を余儀なくされ、施工効率の悪化や天候不順等が複合的に影響し工程を見直したことに加え、建設資機材価格や労務費が高騰していること等により見積総原価が増大し、原価低減や追加工事の獲得が追い付かず、現時点では損益改善の見通しが立たないため多額の損失を計上することになった」
特定の国内大型工事について、施工方法変更、施工効率悪化、天候不順、資材価格・労務費高騰及び追加工事獲得の遅れにより見積総原価が増大し、多額の損失を計上したと記載しています。