Revised forecast
Fiscal year ending March 2026 · Full yearPrevious forecast published Announced on 13 February 2026The bar length represents the relative magnitude of change, based on the item that changed the most in this document. The percentage change shown by the dotted line is calculated from the two reported figures because the company did not provide the rate.
Additional costs will be incurred by the relevant subsidiary. Approximately ¥230 million will be recorded as a provision for losses on construction contracts for expected future losses on construction contracts from the current fiscal year onward. Operating income and ordinary income are expected to remain in line with the previous forecast due to improved profitability in the construction business. However, approximately ¥770 million in costs related to re-erection and other expenses will be recorded as an extraordinary loss, reducing net income for the current fiscal year by a total of approximately ¥1,000 million.
Approximately ¥770 million in costs related to re-erection and other expenses will be recorded as an extraordinary loss. Approximately ¥230 million in expected future losses on construction contracts from the current fiscal year onward will be recorded as a provision for losses on construction contracts, bringing the total to approximately ¥1,000 million. The current estimate of total costs related to remanufacture, re-erection and other expenses is approximately ¥5.0 billion.
| Item | Details |
|---|---|
| Net Sales | ¥66,000 million → ¥66,000 million(0.0%) |
| Operating profit | ¥4,900 million → ¥4,900 million(0.0%) |
| Ordinary income | ¥4,900 million → ¥4,900 million(0.0%) |
| Profit attributable to owners of the parent | ¥3,250 million → ¥2,700 million(-16.9%) |
| Net income per share | 21.15 yen and sen → 20.87 yen and sen |
| Fiscal Period Covered | Fiscal year ending March 2026 |
| Period Covered | Full year |
| Publication date of previous forecast | Announced on 13 February 2026 |
| Previous-period results | Sales: ¥64,553 million; operating income: ¥5,434 million; ordinary income: ¥5,556 million; net income attributable to owners of the parent: ¥3,715 million; earnings per share: ¥28.07 (fiscal year ended March 2025) |
| Reason for the revision | Additional costs will be incurred by the relevant subsidiary. Approximately ¥230 million will be recorded as a provision for losses on construction contracts for expected future losses on construction contracts from the current fiscal year onward. Operating income and ordinary income are expected to remain in line with the previous forecast due to improved profitability in the construction business. However, approximately ¥770 million in costs related to re-erection and other expenses will be recorded as an extraordinary loss, reducing net income for the current fiscal year by a total of approximately ¥1,000 million. |
| Details and amount of extraordinary loss | Approximately ¥770 million in costs related to re-erection and other expenses will be recorded as an extraordinary loss. Approximately ¥230 million in expected future losses on construction contracts from the current fiscal year onward will be recorded as a provision for losses on construction contracts, bringing the total to approximately ¥1,000 million. The current estimate of total costs related to remanufacture, re-erection and other expenses is approximately ¥5.0 billion. |
| Consolidated / non-consolidated | Consolidated |
Items this document does not state (1)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The nonconformity of products manufactured by Kanadevia Corporation, which had been commissioned by a consolidated subsidiary, requires the remanufacture and re-erection of a bridge, resulting in additional costs. Approximately ¥230 million will be recorded as a provision for losses on construction contracts, and approximately ¥770 million as an extraordinary loss. Operating income and ordinary income are expected to remain in line with the previous forecast due to improved profitability in the construction business.