Notice Regarding the Start of Construction of the Grid-Scale High-Voltage Battery Storage Facility "fantasista nagahama PSS (Nagahama Battery Storage Facility)"

Construction of the grid-scale high-voltage battery storage facility “fantasista nagahama PSS (Nagahama Battery Storage Facility)” in Kinomotocho, Nagahama City, Shiga Prefecture, commenced on 16 October 2026. Completion is scheduled for March 2027, with operations scheduled to begin in April of the same year.

Worth reading
57In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Improvement
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Conditional
How definitive the wording is.

Announced details

fantasista nagahama PSS (Nagahama Battery Storage Facility)
Applicable field (uses covered by this announcement)

Grid-scale battery storage business utilizing Japan’s balancing market and other markets

Launch dateApril 2027 (scheduled; commencement of operations)
Relationship between the counterparty and the company
Fantasista Co.,Ltd.1783
Relationship with the Company

スズカ電工株式会社 is responsible for basic design and construction. Capital and personnel relationships have not been disclosed.

Counterpartyスズカ電工株式会社
Location (as indicated in this announcement)

237-1 and 238-1, Senda, Kinomotocho, Nagahama City, Shiga Prefecture

Impact on Business Performance

The Company is reviewing its business plan and other details ahead of the planned commencement of operations in April 2027, and plans to reflect the impact in its earnings forecast for the fiscal year ending September 2027.

The company does not address Contract Value / Offering price.

Announced details
ItemDetails
Names of Products / Services Coveredfantasista nagahama PSS (Nagahama Battery Storage Facility)
Counterpartyスズカ電工株式会社
Relationship with the Companyスズカ電工株式会社 is responsible for basic design and construction. Capital and personnel relationships have not been disclosed.
Launch dateApril 2027 (scheduled; commencement of operations)
Applicable areaGrid-scale battery storage business utilizing Japan’s balancing market and other markets
Location237-1 and 238-1, Senda, Kinomotocho, Nagahama City, Shiga Prefecture
Impact on Business PerformanceThe Company is reviewing its business plan and other details ahead of the planned commencement of operations in April 2027, and plans to reflect the impact in its earnings forecast for the fiscal year ending September 2027.
Items this document does not state (11)
Counterparty overviewContract ValueOffering priceContract DateAward/certification nameAwarding / certifying bodyRegistration number and expiry dateLocation scaleQuantitative EffectsUsage historySource

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The Company has positioned its grid-scale battery storage business as one of its growth businesses and aims to accumulate expertise and know-how in the development, equipment installation and operation of battery storage facilities, linking these efforts to future plans for extra-high-voltage battery storage facilities and AI data centers.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Regarding the Start of Construction of the Grid-Scale High-Voltage Battery Storage Facility "fantasista nagahama PSS (Nagahama Battery Storage Facility)" | Fantasista Co.,Ltd. (1783) timely disclosure | Komori