COMSYS Holdings (1721) · InitiativeAchieved
Construction Base and New Office at NDS Shizuoka Heiwa Building
First written in FY2022-Q3. 1 of 2 entries say "Achieved", first in FY2024-Q2. Latest entry: FY2024-Q2.
2entries
2years
0from disclosures
How it moved
Same theme, other companies
Construction Base and New Office at NDS Shizuoka Heiwa BuildingA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2024-Q2AchievedAnnual report
「NDS Co., Ltd. NDS Shizuoka Heiwa Building (Shizuoka, Shizuoka Prefecture) NDS Group Construction office ¥1,426 million August 2023」
The NDS Shizuoka Heiwa Building construction office was completed in August 2023 at a total investment of ¥1,426 million, completing the plan to improve operational efficiency by consolidating dispersed locations. - FY2022-Q3First statedAnnual report
「NDS Co., Ltd. NDS Shizuoka Heiwa Building (Shizuoka, Shizuoka Prefecture) NDS Group Construction base Office 1,600 398 Internal funds February 2022 August 2023 Improving operational efficiency by consolidating dispersed locations」
The NDS Group finalized its plan to establish a new construction base and office at the NDS Shizuoka Heiwa Building. The total planned investment is ¥1.6 billion, the amount already paid is ¥398 million, and completion is scheduled for August 2023. The project aims to improve operational efficiency by consolidating dispersed locations.