Completion of Production Well Drilling in Ojiya City, Niigata Prefecture
First written in FY2017-Q3. 2 of 7 entries say "Advanced", first in FY2022. Latest entry: FY2025-H1.
No other company in this theme has enough history to compare yet.
- FY2025-H1AchievedAnnual report
「At the end of the previous consolidated fiscal year, the company's plans for the construction of significant facilities included one production well, with a drilling depth of approximately 4,830 m, located in Ojiya, Niigata, with work commencing in August 2023. The project was completed in June 2024.」
One production well in Ojiya, Niigata, with a drilling depth of approximately 4,830 m, was completed in June 2024. - FY2024AdvancedAnnual report
「The one production well at the Nagaoka Office of Japan Petroleum Exploration Co.,Ltd. described in the annual securities report for the fiscal year ended March 2023 was scheduled for completion by June 2024 due to delays in the work schedule.」
After completion of the previous production well in Ojiya, a new production well with a drilling depth of approximately 4,830 m was planned, with completion scheduled for June 2024. The amount already paid was ¥2,030 million, and total planned investment was ¥3,600 million. - FY2023AchievedAnnual report
「The one production well at the Nagaoka Office of Japan Petroleum Exploration Co.,Ltd. described in the annual securities report for the fiscal year ended March 2022 was completed in May 2023.」
The Ojiya production well project was completed in May 2023 after the scheduled completion date was pushed back and the planned investment amount was revised. - FY2023-Q3SoftenedAnnual report
「Among the company's plans at the end of the previous consolidated fiscal year for the construction of significant facilities was one production well, with a drilling depth of approximately 5,300 m, located in Ojiya, Niigata, with total planned investment of ¥5.9 billion and completion scheduled for February 2023. Following a review of the accounting treatment, total planned investment was changed to ¥4.1 billion. In addition, completion was scheduled for May 2023 due to delays in the work schedule.」
For the production well project in Ojiya, planned investment was reduced from ¥5.9 billion to ¥4.1 billion, and the scheduled completion was postponed from February 2023 to May of the same year. - FY2023-Q2SoftenedAnnual report
「Among the company's plans at the end of the previous consolidated fiscal year for the construction of significant facilities was one production well, with a drilling depth of approximately 5,300 m, located in Ojiya, Niigata, and total planned investment of ¥5.9 billion. Following a review of the accounting treatment, total planned investment was changed to ¥4.4 billion.」
For the production well project in Ojiya, total planned investment was reduced from ¥5.9 billion to ¥4.4 billion. - FY2022AdvancedAnnual report
「One production well (drilling depth: approximately 5,300 m) 5,900 687 Internal funds From June 2022 To February 2023」
A plan for one production well in Ojiya, with a drilling depth of approximately 5,300 m, was newly specified, with work beginning in June 2022, completion scheduled for February 2023, and planned investment of ¥5.9 billion disclosed. - FY2017-Q3First statedAnnual report
「At the end of the previous consolidated fiscal year, the company's plans for the construction of significant facilities included one production well, with a drilling depth of approximately 5,100 m, located in Ojiya, Niigata, with construction commencing in March 2016. The project was completed in October 2016.」
The company disclosed the completion in October 2016 of one production well in Ojiya, with a drilling depth of approximately 5,100 m.