Construction of Osaka No. 1 Data Center
First written in FY2016. 5 of 8 entries say "Advanced", first in FY2018. Latest entry: FY2020-Q3.
No other company in this theme has enough history to compare yet.
- FY2020-Q3RestatedAnnual report
「Full-scale operation of the Osaka No. 1 Data Center」
The company continued to describe revenue growth through the full-scale operation of the Osaka No. 1 Data Center as part of its business development. - FY2020-Q2RestatedAnnual report
「The company sought to expand revenue through the full-scale operation of the Osaka No. 1 Data Center and other initiatives.」
The company continued to report the full-scale operation of the Osaka No. 1 Data Center and its use to expand revenue, as in the previous quarter. - FY2020-Q1AdvancedAnnual report
「The company sought to expand revenue through the full-scale operation of the Osaka No. 1 Data Center and other initiatives.」
The Osaka No. 1 Data Center progressed from the construction and launch-of-operations stages to full-scale operation. - FY2019AdvancedAnnual report
「The company also actively pursued the development of frontier domains from a medium- to long-term perspective, including the launch of operations at the Osaka No. 1 Data Center in June 2018.」
The Osaka No. 1 Data Center progressed from the construction stage to the launch of operations in June 2018. - FY2019-Q2AdvancedAnnual report
「During the six-month period ended in the second quarter, the Osaka No. 1 Data Center, which 株式会社ミライト・テクノロジーズ had been planning as of the end of the previous consolidated fiscal year, was completed except for part of the facility.」
The Osaka No. 1 Data Center progressed from the planning stage at the end of the previous consolidated fiscal year to the stage of completion, except for part of the facility. - FY2019-Q1AdvancedAnnual report
「We also actively pursued the expansion of new businesses, including the start of operations at Osaka No. 1 Data Center in June 2018.」
Osaka No. 1 Data Center progressed from the construction-plan stage to the start of operations in June 2018. - FY2018AdvancedAnnual report
「During the consolidated fiscal year, total capital investment, including investment in intangible fixed assets, amounted to ¥12.626 billion. The principal investment was for construction of a data center.」
Capital investment of ¥12.626 billion was made, mainly for data center construction. The Osaka No. 1 Data Center was scheduled for completion in May 2018, with total planned investment of ¥18.428 billion. - FY2016First statedAnnual report
「㈱ミライト・テクノロジーズ Osaka No. 1 Data Center (Nishi-ku, Osaka) Buildings and structures 18,000 125 Internal funds, borrowings from financial institutions, etc. October 2016 Fiscal 2018」
Capital investment plan with a total planned investment of ¥18 billion, commencing in October 2016 and scheduled for completion in fiscal 2018.