Full-scale development of non-FIT power plants and green power supply

First written in FY2021. 4 of 14 entries say "Advanced", first in FY2023-Q1. Latest entry: FY2026.

14entries
6years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2021 – FY2022-Q3OtherFY2023-Q2 – FY2024-Q1AdvancedFY2024-Q2 – FY2024-Q3OtherFY2025-H12021: 12022: 320222023: 420232024: 320242025: 120252026: 22026
Same theme, other companies
Development of Post-FIT PPA and High-Value-Added Renewable Energy BusinessesA theme 11 companies write about · 0 as a headwind · 14 as a tailwind

0 other companies' latest entry also says "Other".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026Shortfalls against delivery plans and declining profitability; suspension of new utility-scale solar developmentAnnual report

    「In the non-FIT solar power plant development business, many projects were scheduled to begin power supply from April 2026. Because the number of deliveries through the third quarter was below plan, the company accelerated the delivery of completed projects in the fourth quarter, but full-year results fell below the initial plan. Profitability in the business also fell below the previous fiscal year because profitability declined for some projects. The company has been handling only projects prepared to date for ground-mounted utility-scale solar plants and is not undertaking new development.」

    Full-year deliveries in non-FIT power plant development fell below the initial plan, and profitability deteriorated because profitability declined for some projects. The company adopted a policy of limiting ground-mounted utility-scale solar plants to projects already prepared and not undertaking new development.
  2. FY2026-H1AdvancedAnnual report

    「Many projects in the non-FIT solar power facility development business are scheduled to begin supplying power from the new fiscal year, beginning in April 2026, and sales fell below plan. More than 400 completed non-FIT power facilities are scheduled to be sold in the third and fourth quarters.」

    Completed non-FIT power plants accumulated to more than 400 sites, and the company indicated plans to sell them in the third and fourth quarters. However, sales for the six-month period fell below plan because many projects were scheduled to begin power supply from the new fiscal year.
  3. FY2025-H1Delivery delays due to heavy snow and cold waves; recovery expected in the second halfAnnual report

    「Throughout the first half, both the industrial solar power facility contracting business and the non-FIT solar power facility development and sales business steadily accumulated projects and showed construction progress in line with plan. However, prolonged heavy snowfall, cold waves and unusually low temperatures in February repeatedly froze roads and construction sites, particularly in mountainous areas, causing delays in construction and final inspections. As a result, the handover of properties with sales of approximately ¥2.0 billion was pushed back to the third quarter or later.」

    While projects and construction in progress accumulated in the self-consumption contracting business and the non-FIT development and sales business, deliveries of projects worth approximately ¥2.0 billion were pushed back to the third quarter or later because of heavy snow, cold waves and unusually low temperatures. The company stated that the impact on the full-year plan would not be significant and that it could be made up in the second half.
  4. FY2024-Q3AdvancedAnnual report

    「The non-FIT power facility development and sales business recorded sales of approximately ¥11.6 billion, up 335.0% year on year, and the number of construction projects also increased steadily. A substantial number of completed properties awaiting handover has accumulated, and we expect to secure a sufficient backlog of projects against the full-year plan. In addition to low-voltage projects, results from high-voltage non-FIT power facilities are scheduled to be recognized from the fourth quarter.」

    The non-FIT power plant development and sales business recorded sales of approximately ¥11.6 billion, up 335.0% year on year, while the number of construction projects, completed projects and the project backlog increased. The company planned to begin recognizing results from high-voltage non-FIT power plants in addition to low-voltage projects from the fourth quarter.
  5. FY2024-Q2AdvancedAnnual report

    「The non-FIT power facility development and sales business temporarily slowed because of the administrative workload following the handover of numerous properties in the fourth quarter of the previous fiscal year. Nevertheless, sales rose 317.2% year on year to approximately ¥7.0 billion, and the number of construction projects also increased steadily. Although sales through the second quarter fell short of plan, a substantial number of completed properties awaiting handover has accumulated, and we expect to secure a sufficient backlog of projects against the full-year plan. In addition to continuing to focus on maintaining and reducing construction costs, average sales per project have remained above plan, and the business is expected to make an increasing contribution to profit.」

    The non-FIT power plant development and sales business temporarily slowed due to the administrative workload, and sales through the second quarter fell short of plan. However, sales increased 317.2% year on year to approximately ¥7.0 billion, while the number of construction projects, the project backlog and average sales per project progressed.
  6. FY2024-Q1Sharp sales increase; temporary slowdown due to administrative workloadAnnual report

    「The non-FIT power facility development and sales business temporarily slowed because of the administrative workload following the handover of numerous properties in the fourth quarter of the previous fiscal year. Nevertheless, sales rose 457.5% year on year to approximately ¥1.9 billion, and the number of construction projects also increased steadily.」

    Although the pace temporarily slowed because of the administrative workload following the delivery of numerous projects, sales increased 457.5% year on year to approximately ¥1.9 billion, and the number of construction projects also increased.
  7. FY2023Full-year sales recognition; first-half delays not recoveredAnnual report

    「The backlog of projects for which grid interconnection responses had been obtained accumulated broadly in line with plan, and construction starts also increased steadily each month. Quarterly sales were approximately ¥300 million in the first quarter, ¥1.3 billion in the second quarter, ¥1.0 billion in the third quarter and ¥7.8 billion in the fourth quarter. Ultimately, the company reached the expected level of monthly completions, but was unable to recover the delays incurred in the first half.」

    In non-FIT power plant development, the project backlog and construction starts increased, and fourth-quarter sales grew to approximately ¥7.8 billion. However, the delays in the first half of the fiscal year were not recovered.
  8. FY2023-Q3Increase in construction starts, with shortfalls against the planned pace continuingAnnual report

    「In the non-FIT power plant development and sales business, delays in receiving grid interconnection responses from electric utilities, which had been a major bottleneck through the previous fiscal year, have generally improved. However, obtaining the various permits and approvals required to develop construction sites is taking longer than expected. In addition, following the introduction of a new system for small-scale business electrical installations, basic information filings and pre-use self-inspections have been required since 20 March 2023 for low-voltage power plants below 50 kW, further increasing the steps required before grid interconnection. The company regards these requirements as necessary social demands for the future expansion of renewable energy and is carefully addressing the resulting issues. Despite these conditions, the order environment remains strong, and the backlog of projects for which grid interconnection responses have been obtained has accumulated broadly in line with plan. The number of construction starts has also increased steadily each month, but remains below the planned pace, and completion and delivery may be delayed into the next fiscal year to a corresponding extent.」

    Delays in grid interconnection responses have generally improved, and the project backlog and monthly construction starts have increased. However, permits, approvals and the new system have increased the number of steps, construction starts remain below the planned pace, and completion and delivery are expected to spill over into the next fiscal year.
  9. FY2023-Q2Improvement in grid interconnection response delays; construction delays due to permits and approvalsAnnual report

    「In the non-FIT power plant development and sales business, delays in receiving grid interconnection responses from electric utilities, which had been a major bottleneck through the previous fiscal year, have generally improved. However, obtaining the various permits and approvals required to develop construction sites is taking longer than expected. In addition, following the introduction of a new system for small-scale business electrical installations, basic information filings and pre-use self-inspections have been required since 20 March 2023 for low-voltage power plants below 50 kW, further increasing the steps required before grid interconnection. Although the project backlog for which grid interconnection responses have been obtained has accumulated broadly in line with plan, the number of construction starts is below the planned pace, and completion and delivery are expected to be delayed accordingly.」

    In non-FIT power plant development, delays in grid interconnection responses have generally improved, and the backlog of projects for which responses have been obtained has accumulated broadly in line with plan. However, permits, approvals and the new system have increased the number of steps, construction starts are below the planned pace, and completion and delivery are expected to be delayed.
  10. FY2023-Q1AdvancedAnnual report

    「Although the non-FIT power plant development business has not yet generated significant revenue, construction plans for 1,100 to 1,200 plants have been finalized against this year's development target of 3,000 plants, putting us in a position to aim for the target through further accumulation of projects.」

    For non-FIT power plant development, construction plans for 1,100 to 1,200 projects had been finalized against the annual development target of 3,000 projects. The company explained that sales recognition had not yet reached full scale, but conditions remained conducive to achieving the target.
  11. FY2022-Q3RestatedAnnual report

    「Against this backdrop, our group, while advancing its existing energy-generation business of sourcing materials for, constructing, selling and providing O&M (operations and maintenance) services for solar power generation systems to local companies and governments, expanded into total energy solutions including energy-saving services using LED lighting and air-conditioning equipment, while also actively pursuing new businesses for the post-FIT renewable energy market, including self-consumption power plants, development of non-FIT power plants, green electricity supply and the revitalization and resale of existing utility-scale solar facilities.」

    The company continues to pursue a group of new businesses for the post-FIT market, comprising self-consumption power plants, non-FIT power plants, green power supply, and the refurbishment and resale of existing utility-scale solar plants.
  12. FY2022-Q2RestatedAnnual report

    「While promoting its distributed energy business, which has traditionally involved the procurement, construction, sale and O&M (operations and maintenance) of materials for solar power generation systems for local companies and municipalities, the group has expanded total energy solutions such as energy-saving businesses using LED lighting and air-conditioning equipment. It has also actively pursued new businesses for the post-FIT renewable energy market, including self-consumption power plants, the development of non-FIT power plants, green power supply, and the refurbishment and resale of existing utility-scale solar plants.」

    The company continues to pursue a group of new businesses for the post-FIT market, comprising self-consumption power plants, non-FIT power plants, green power supply, and the refurbishment and resale of existing utility-scale solar plants.
  13. FY2022-Q1RestatedAnnual report

    「The company has actively pursued new businesses for the post-FIT renewable energy market, including the full-scale development of non-FIT power plants, green power supply, and the refurbishment and resale of existing utility-scale solar plants.」

    For the post-FIT market, the company continues to pursue a group of integrated new businesses comprising the construction of non-FIT power plants, green power supply, and the refurbishment and resale of existing utility-scale solar plants.
  14. FY2021First statedAnnual report

    「The company has actively pursued new businesses for the post-FIT renewable energy market, including the full-scale development of non-FIT power plants, green power supply, and the refurbishment and resale of existing utility-scale solar plants.」

    For the post-FIT market, the company reported the full-scale rollout of a group of integrated new businesses comprising the construction of non-FIT power plants, green power supply, and the refurbishment and resale of existing utility-scale solar plants.
Moved together

"Utility-scale solar maintenance business" moved the same way as this thread, in the same document, in 4 of its 14 moves.

422★123
  1. ★This thread
  2. 1Utility-scale solar maintenance business4×
  3. 2Electricity Sales and In-House Power Generation2×
  4. 3Shareholder Returns Through Dividends and Share Repurchases2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for West Holdings yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.