- FY2026AdvancedAnnual report
「By making maximum use of O&M and the West FIT framework, the company will substantially increase its future sources of green power procurement without increasing its asset base.」
The Company specified its policy of using West FIT and O&M to increase future green power procurement sources without increasing its asset base. - FY2023-Q1AdvancedAnnual report
「In the development and sales business for non-FIT power plants, the Company focused on securing a large number of construction sites and applying to power companies for grid connection. After struggling with delays in receiving grid connection responses, conditions have finally begun to improve and construction is gradually getting underway.」
For the development of non-FIT power plants using West FIT, the Company advanced site acquisition and grid connection applications, while delays in grid connection responses improved and construction gradually began. - FY2022-Q3RestatedAnnual report
「As a business model independent of the FIT scheme, in addition to promoting the self-consumption model, we advanced the development of non-FIT power facilities using the private FIT mechanism, WEST FIT, under which our group purchases electricity generated by solar power facilities, and focused on securing large volumes of land for constructing these facilities and submitting grid interconnection applications to electric power companies.」
The Company continued to focus on developing non-FIT power plants using West FIT, securing construction sites and applying to power companies for grid connection. - FY2022-Q2RestatedAnnual report
「As a business model independent of the FIT scheme, in addition to promoting the self-consumption model, we advanced the development of non-FIT power facilities using the private FIT mechanism, WEST FIT, under which our group purchases electricity generated by solar power facilities, and focused on securing large volumes of land for constructing these facilities and submitting grid interconnection applications to electric power companies.」
The Company continued developing non-FIT power plants using West FIT, focusing on securing construction sites and applying to power companies for grid connection. - FY2022-Q1RestatedAnnual report
「As a business model independent of the FIT scheme, we promoted the rollout of a green power business model using a new mechanism, WEST FIT, under which our group purchases electricity generated by solar power facilities, in addition to expanding the self-consumption model, and focused on securing large volumes of land for constructing these power facilities and submitting grid connection applications in coordination with electric power companies.」
The Company continued to roll out the green power business model using West FIT, focusing on securing construction sites and applying to power companies for grid connection. - FY2021AdvancedAnnual report
「As post-FIT growth strategies, we will make every effort to expand the installation of solar power generation facilities by promoting the adoption of green power business models centered on West FIT, self-consumption models and mega-solar redevelopment, and by proposing battery-equipped solar power generation systems for self-consumption to local governments nationwide.」
The Company positioned the green power business model using West FIT as the core of its post-FIT growth strategy and specified its areas of expansion as self-consumption, megasolar redevelopment and facilities equipped with batteries for local governments. - FY2021-Q2AdvancedAnnual report
「In preparation for the end of the FIT scheme, we promoted the rollout of a green power business model, in addition to expanding the self-consumption model, using a new mechanism, WEST FIT, under which our group purchases electricity generated by solar power facilities.」
The Company continued to roll out the green power business model using West FIT that it developed in the previous fiscal year. - FY2021-Q1AdvancedAnnual report
「In preparation for the end of the FIT scheme, we promoted the rollout of a green power business model, in addition to expanding the self-consumption model, using a new mechanism, WEST FIT, under which our group purchases electricity generated by solar power facilities.」
The Company continued to roll out the green power business model using West FIT that it developed in the previous fiscal year. - FY2020First statedAnnual report
「As preparation for the end of the FIT system, while working to further reduce total generation costs and promote the self-consumption model, we developed a business model for the green electricity business using a new mechanism, West FIT, under which our group purchases electricity generated by solar power.」
As a growth strategy after the end of the FIT system, the Company developed a green power business model using West FIT, under which the Group purchases electricity generated by solar power facilities.