Risk of construction delays caused by typhoons and other events
First written in FY2016. 2 of 4 entries say "Materialised", first in FY2017. Latest entry: FY2026.
West Holdings moved to the "Worse" side of this theme in 2017, 3 years before the typical company in this theme (2020).
The whole theme swung hardest in 2025: 3 of 9 companies on the "Worse" side.
1 other company's latest entry also says "Worsened".
- FY2026WorsenedAnnual report
「As natural disasters such as torrential rains have become more severe and frequent in recent years, requirements for developing ground-mounted solar power plants have become stricter, including consideration of hazard conditions and the local environment and consultations with local governments.」
The disclosure describes the intensification and increasing frequency of torrential rain and other severe weather and the tightening of development requirements as risks relating to weather and natural disasters. - FY2025-H1MaterialisedAnnual report
「Prolonged heavy snowfall in February, cold waves and unusually low temperatures caused repeated freezing of roads and construction sites, particularly in mountainous areas. This delayed construction and final inspections, and the delivery of properties with sales of approximately ¥2 billion was pushed back to the third quarter or later.」
Weather-related construction delay risks actually materialised in the form of frozen roads and construction sites caused by heavy snowfall, cold waves and unusually low temperatures, delays in construction and final inspections, and delivery delays involving approximately ¥2 billion. - FY2017MaterialisedAnnual report
「In the mega-solar business as well, land development work was delayed by prolonged adverse weather and other factors, and projects totalling 3.6MW (2 locations) in the Kyushu region, 1.1MW in the Chugoku region and 1.2MW in the Tohoku region were carried over to the following fiscal year.」
Although not attributable to a specific event such as a typhoon, delays in land development work caused by prolonged adverse weather occurred, and multiple projects were carried over to the following fiscal year. - FY2016First statedAnnual report
「However, repeated typhoons in August caused construction delays.」
The disclosure states that repeated typhoons in August actually caused construction delays.