Risk of delays in utility-scale solar development due to permits and local consensus
First written in FY2018. 1 of 3 entries say "Materialised", first in FY2023-Q2. Latest entry: FY2026.
West Holdings moved to the "Worse" side of this theme in 2023.
0 other companies' latest entry also says "Worsened".
- FY2026WorsenedAnnual report
「As natural disasters such as torrential rains have become more severe and frequent in recent years, the company is placing emphasis on hazard conditions, the local environment, safety and business continuity in developing ground-mounted solar power plants, while proceeding with greater care in selecting development projects.」
In addition to permits and local consensus, the company emphasized the increasing severity of natural disasters, hazard conditions, and consideration for the local environment and safety as factors in selecting development projects. - FY2023-Q2MaterialisedAnnual report
「In addition to the fact that obtaining various permits for construction sites was taking longer than expected, a new system for small-scale electrical facilities came into force. From 20 March 2023, even low-voltage power plants below 50 kW were required to file basic information and a pre-use self-inspection notification, further increasing the steps required before grid connection.」
Obtaining various permits for construction sites took longer than expected, and the new system for low-voltage power plants further increased the steps required before grid connection. - FY2018First statedAnnual report
「If obtaining permits or reaching agreement with local residents takes longer than anticipated and delays occur in project plans, this could affect our results.」
The company separately stated for the first time that obtaining permits for farmland conversion, forest development and other matters, as well as reaching agreement with landowners and local residents, could delay utility-scale solar projects.