West Holdings (1407) · RiskMaterialised
Occurrence of Construction Delays Caused by Typhoons
First written in FY2016. 3 of 3 entries say "Materialised", first in FY2016. Latest entry: FY2025-H1.
3entries
10years
0from disclosures
How it moved
Same theme, other companies
Risk of construction delays and additional costs due to natural disastersA theme 20 companies write about · 21 as a headwind · 0 as a tailwind
West Holdings moved to the "Worse" side of this theme in 2016, 3 years before the typical company in this theme (2019).
The whole theme swung hardest in 2025: 3 of 6 companies on the "Worse" side.
5 other companies' latest entry also says "Materialised".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 20 companies compared. The sentences above are computed from all 20.Full recordFilings, disclosures and news, newest first
- FY2025-H1MaterialisedAnnual report
「2月の長期間にわたる大雪と寒波・異常低温の影響により、特に山間部において路面や建設用地の凍結が相次いだことから、工事や最終検査に遅れが生じることとなり、売上高約20億円の物件引渡が第3四半期以降にずれ込むこととなりました。」
台風・天候不順に続き、大雪、寒波及び異常低温による路面・建設用地の凍結が発生し、工事・最終検査の遅延と約20億円の物件引渡し延期につながった。 - FY2017MaterialisedAnnual report
「メガソーラー事業においても天候不順が長引くなどにより造成工事が遅れ、具体的案件として九州地方で3.6MW(2カ所)、中国地方で1.1MW、東北地方で1.2MWを翌期に繰り延べました。」
長期化した天候不順による造成工事遅延と、合計5.9MWの案件の翌期繰り延べが発生した。 - FY2016MaterialisedAnnual report
「However, repeated typhoons in August caused construction delays.」
Construction delays actually occurred because of repeated typhoons in August.