West Holdings (1407) · RiskMaterialised
Risk of Prolonged Permitting and Community Consensus-Building for Mega-Solar Development
First written in FY2018. 1 of 3 entries say "Restated". Latest entry: FY2023-Q2.
3entries
6years
0from disclosures
How it moved
Same theme, other companies
Risk of Delays in Development Permits and Approvals, Environmental Assessments, and Consensus-Building with Local StakeholdersA theme 7 companies write about · 8 as a headwind · 0 as a tailwind
West Holdings moved to the "Worse" side of this theme in 2023.
0 other companies' latest entry also says "Materialised".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2023-Q2MaterialisedAnnual report
「非FIT発電所の開発販売事業におきましては、前年度まで大きなボトルネックとなっていた電力会社との接続連系回答の遅延は概ね改善しているものの、建設用地の開発にかかる各種許認可の取得に想定以上の時間を要する状況となっていることに加え、小規模事業用電気工作物の新制度が施行され、2023年3月20日より50kW未満の低圧発電所についても、基礎情報と使用前自己確認の届出が義務付けられたことから、接続連系に至るまでの工程が更に増加することとなりました。」
接続連系回答の遅延は概ね改善した一方、建設用地の許認可取得に想定以上の時間を要し、新制度による届出義務も加わって接続連系までの工程が増加した。 - FY2021RestatedAnnual report
「許認可取得や地域住民との合意に想定した以上の時間を要し、プロジェクト計画に遅れが生じる場合には、業績に影響を与える可能性があります。」
メガソーラー開発における許認可取得及び地域住民との合意形成の長期化リスクを継続して開示している。 - FY2018First statedAnnual report
「許認可取得や地域住民との合意に想定した以上の時間を要し、プロジェクト計画に遅れが生じる場合には、業績に影響を与える可能性があります。」
農地転用・林地開発等の許認可取得や地権者・地域住民との合意形成の長期化を、メガソーラー開発の個別リスクとして新たに開示した。