Review of the feed-in tariff scheme and decline in purchase prices
First written in FY2016-Q3. 3 of 9 entries say "Restated". Latest entry: FY2021.
West Holdings moved to the "Worse" side of this theme in 2016, 3 years before the typical company in this theme (2019).
12 other companies' latest entry also says "Restated".
- FY2021RestatedAnnual report
「The Group's renewable energy business may be affected by the level of the purchase price and the purchase period under the Feed-in Tariff (FIT) scheme for electricity under the Act on Special Measures Concerning Procurement of Electricity from Renewable Energy Sources by Electricity Utilities, as well as delays in responding to applications for grid connection of renewable energy power generation facilities, pending responses and the status of rules concerning refusals to connect.」
The company continues to disclose the risk that FIT prices, purchase periods, and delays in grid interconnection and related matters may affect performance. - FY2018RestatedAnnual report
「The Group's renewable energy business may be affected by the level of the purchase price and the purchase period under the Feed-in Tariff (FIT) scheme for electricity under the Act on Special Measures Concerning Procurement of Electricity from Renewable Energy Sources by Electricity Utilities, as well as delays in responding to applications for grid connection of renewable energy power generation facilities, pending responses and the status of rules concerning refusals to connect.」
The company continues to disclose FIT prices, purchase periods, and delays, pending responses, and refusals to connect to the grid as risks. - FY2018-Q2Continued price declines and improvement in construction delaysAnnual report
「The industrial solar power generation business has construction plans exceeding 350 MW over the next 5 years. However, during the first quarter accounting period, the amended FIT Act, which came into force in April 2017, had a significant effect on construction start and completion schedules. During the second quarter accounting period, signs of improvement in these conditions were observed. In the second half of the fiscal year, we expect to make up for the delays incurred in the first half and complete construction as originally planned.」
Delays to construction schedules caused by the amended FIT Act showed signs of improvement in the second quarter, and the company expected to make up for the delays in the second half. Meanwhile, declines in electricity sales prices continued. - FY2018-Q1RestatedAnnual report
「In the industrial solar power generation business, the Act Partially Amending the Act on Special Measures Concerning Promotion of Utilization of Electricity from Renewable Energy Sources (the amended FIT Act), which took effect in April 2017, had a significant impact on construction start and completion schedules, causing substantial delays in the business plan.」
The impact of the amended FIT Act on construction schedules and the substantial delays to business plans were described as events continuing from the previous fiscal year. - FY2017MaterialisedAnnual report
「For the industrial solar power generation business, the amended FIT Act, which came into force in April this year, had a significant effect on the construction start and completion schedule, resulting in substantial delays to business plans. In the mega-solar business, site development work was also delayed by prolonged adverse weather conditions and other factors. Specifically, projects totaling 3.6 MW at 2 sites in the Kyushu region, 1.1 MW in the Chugoku region, and 1.2 MW in the Tohoku region were deferred to the following fiscal year.」
The amended FIT Act affected construction schedules, and site development work was actually delayed by adverse weather conditions. Projects totaling 5.9 MW were deferred to the following fiscal year. - FY2017-Q3WorsenedAnnual report
「In the industrial solar power generation business, project plans overall have been delayed because the review period for new certification applications and transition procedures for deemed certifications under the new FIT scheme effective from April this year has become longer, while discussions on development plans for mega-solar projects continue to require additional time.」
Review periods for new certification applications and deemed-certification transition procedures under the new fixed-price purchase scheme became prolonged, and discussions on development plans for mega-solar projects also took longer, resulting in widespread delays to business plans. - FY2017-Q1MaterialisedAnnual report
「While the operation of the FIT scheme was being reviewed, the pre-use self-inspection system for electricity connection procedures was introduced under the amended Ordinance for Enforcement of the Electricity Business Act, resulting in delays in the completion and start of operations of some solar power generation facilities.」
Following a review of the operation of the FIT scheme and the launch of a new system accompanying the enforcement of the amended Order for Enforcement of the Electricity Business Act, delays in the completion and start of operations of some facilities actually occurred. - FY2016WorsenedAnnual report
「Amid a review of the operation of the feed-in tariff scheme, we pursued a locally focused partner strategy and conducted sales activities centered on information provided by financial institutions, major tax-accounting firms, and builders across Japan. Although purchase prices declined, we continued to receive orders steadily. The Group's solar power generation business may be affected by the level of purchase prices and the purchase period under the feed-in tariff scheme for electricity established by the Act on Special Measures Concerning the Procurement of Electricity from Renewable Energy Sources by Operators of Electric Utilities, as well as by delays in responses to applications for grid interconnection for renewable energy generation facilities, pending responses, and the status of rules concerning refusals to connect.」
The company reconfirmed that a decline in purchase prices had occurred and specified FIT-related risk factors, including delayed or pending responses to grid interconnection applications and refusals to connect. - FY2016-Q3First statedAnnual report
「Amid revisions to the operation of the feed-in tariff system, we pursued a local partner strategy and conducted sales activities primarily using information provided by financial institutions, major accounting firms and homebuilders nationwide. Although purchase prices declined, we continued to secure orders steadily.」
The company described a review of the operation of the feed-in tariff (FIT) scheme and a decline in purchase prices. The decline in purchase prices was presented as an event that had actually occurred.