Expansion of Production Facilities at Trans Ocean Products' Head Office Plant
First written in FY2023. 1 of 2 entries say "Softened", first in FY2025. Latest entry: FY2025.
No other company in this theme has enough history to compare yet.
- FY2025SoftenedAnnual report
「Trans Ocean Products, Inc. Headquarters plant and production facilities Total ¥3,876 million Amount in the following fiscal year ¥1,371 million Scheduled start December 2023 Scheduled completion December 2025 Additional capacity after completion: Production volume 3,400 tonnes」
The capital investment plan was updated from a total of ¥4,911 million with completion scheduled for April 2025 to ¥3,876 million with completion scheduled for December 2025. The scheduled completion date and investment amount have changed. - FY2023First statedAnnual report
「Trans Ocean Products, Inc. Headquarters plant Marine resources business Headquarters plant and production facilities Total ¥4,911 million Amount in the following fiscal year ¥2,429 million Scheduled start December 2023 Scheduled completion April 2025 Additional capacity after completion: Production volume 3,402 tonnes」
The Company first disclosed a capital investment plan for its U.S. headquarters plant and production facilities totaling ¥4,911 million, scheduled to begin in December 2023 and be completed in April 2025, with production capacity of 3,402 tonnes.